Belmont School Will Be Completed

It's already the costliest High School ever built, with over $175 million spent on it so far. It has been put on hold for the last 4 years due to it being built on top of a major earthquake fault and an oil field that is leaching methane and hydrogen sulfide gas. The plan as it stands now is to tear down 2 buildings that are directly above the fault and build 2 more elsewhere, as well as install pipes and monitoring systems to keep the toxic gasses in check.

Belmont School Will Be Completed

It's already the costliest High School ever built, with over $175 million spent on it so far. It has been put on hold for the last 4 years due to it being built on top of a major earthquake fault and an oil field that is leaching methane and hydrogen sulfide gas. The plan as it stands now is to tear down 2 buildings that are directly above the fault and build 2 more elsewhere, as well as install pipes and monitoring systems to keep the toxic gasses in check.